Clean Energy for Latin America

Langui Hydroelectric Power Plant

Plants in Operation

The Langui Power Plant is 6.2 MW hydroelectric power plant located in the Hercca River in Sicuani, Cusco in southern Peru. It was originally built in 1970 and was expanded twice, first to 3.2 MW later on to 6.2 MW.

Aluz acquired the plant in June 2009 and made the second expansion between 2014 and 2015.

Langui Hydroelectric Power Plant

Technical Data

Energy
Production 30,000 MWh/Año

Installed
Capacity 6.2 MW

Gross
Head 116 mts.

Design
Flow 6.3 m³/s

Langui Lake
Reservoir 30,000,000 m³

Transmission
Line 22,9 kV 12 Kms.

The energy and power generated by Langui are sold to Electro Sur Este S.A. through a long-term Power Purchase Agreement (PPA).

We are Clean Energy Renewable Energy